HAWAII REGIONAL SECURITY OPERATION CENTER
| Project Name: | Hawaii Regional Security Operation Center |
| Location: | US Naval Computer and Telecommunications Area Master Station Pacific Wahiawa, Hawaii |
| Contract Award Date: | 11-7-07 |
| Construction Cost: |
$320,000,000 |
| Key Personnel: | Project Manager: Art Aoki Project Engineer: Craig Yamada, Bernard Layugan, Albino Prieto General Foreman:Â Walter Ishida Job Foreman:Â Gerard Iseri |
| Subcontractors: | None |
Project Description:
This new state of the art facility is part of the largest construction contract in the history of the Naval Engineering Facility Command. A design build project, consisting of two new buildings, a 234,000 sq. ft., two story Operations Building and a Visitors Control Center. The scope includes data center design work, new power systems, lighting, security conduit system, complete communication, telephone, data and conduit requirements. A-1 A-Lectrician also provided infrastructure support and coordination of the site electrical work.